Generator FAT Acceptance Criteria: Pass or Fail Guide
A diesel generator set or alternator passes FAT only when valid test results satisfy the approved contract, technical specification, applicable standards, project requirements, and agreed test procedure. Voltage, frequency, current, insulation, protections, temperatures, and operating condition must be judged against configuration-specific limits—not an unsupported universal tolerance.
- Freeze the governing documents and acceptance limits before testing.
- Confirm the tested configuration, load, environment, instruments, and measurement uncertainty.
- Record failures, corrective action, retesting, approvals, and shipment-release status.
Establish the reference hierarchy
Use the signed contract and approved specification first, followed by applicable regulatory requirements, incorporated standards, approved drawings and data sheets, and the agreed procedure. Resolve conflicts in writing. See the complete FAT process guide for the wider workflow.
Validate the test evidence
Verify equipment identity, rating, duty, fuel, power factor, load steps, ambient conditions, instrument status, and raw readings. Use the complete FAT checklist to confirm that required items were not omitted.
Classify and release
Mark each item pass, fail, or pending clarification. A failed or borderline result needs documented review, disposition, corrective action where required, and witnessed retesting before release.
No. Limits depend on rating, performance class, duty, application, configuration, contract, and incorporated standards.
No. The test voltage, winding temperature, correction method, equipment condition, and governing criterion must also be verified.
Only if the contract permits an authorized concession or conditional release and the deviation, risk, responsibility, and close-out requirement are documented.
Acceptance standards and performance indicators
The International Organization for Standardization states in ISO 8528-5 that generating-set design and performance criteria address the combination of engine and alternator. This supports evaluating the assembled set and its declared performance class rather than applying an alternator-only value.
The ISO overview of ISO 8528-6 covers generating-set test methods. It supports agreeing the procedure, test conditions, measurements, and acceptance evidence before treating a result as comparable.
| FAT item | Acceptance basis | Required evidence |
|---|---|---|
| Voltage and frequency | Declared rating, performance class, steady-state and transient limits | Load points, step response, recovery record |
| Current and phase balance | Approved load and configuration | Per-phase readings and load-bank data |
| Insulation and safety | Specified method and applicable machine requirements | Test voltage, temperature, readings, safety checks |
| Protection and shutdown | Approved cause-and-effect schedule | Set points, simulated condition, alarm and trip record |
| Mechanical operation | Approved limits and inspection criteria | Leak, vibration, noise, temperature and visual records |
The International Electrotechnical Commission describes ratings and performance requirements for rotating electrical machines in IEC 60034-1. For alternator FAT, this proves that evaluation must match the machine rating and specified operating conditions.
The IEEE recommended practice IEEE Std 43 addresses insulation-resistance testing of electric machinery. Its defined test practice supports recording temperature and method instead of accepting an isolated resistance number.
Power rating, application, and nonconformity
Standby, prime, continuous-duty, motor-starting, data-center, and unbalanced-load applications can impose different approved criteria. Buyers should therefore verify rating definitions, load profile, power factor, ambient conditions, transient requirements, and protection logic for the exact supplied configuration.
When a result is outside a limit—or too close to it for measurement uncertainty to be ignored—open a nonconformity. Do not average away a failed phase or substitute a later undocumented reading. Record disposition, repair or adjustment, repeat-test conditions, witnesses, and approval. Shipment release should reference the signed test record; a consistent generator test report template helps preserve that evidence.
Diesel Generator FAT Report Template and Guidelines
Diesel Generator FAT Staged Load Test Procedure